Alert 02.27.26
Alert
Alert
10.21.26
January 1, 2027, is less than three months away. On that date, Defense Federal Acquisition Regulation Supplement (DFARS) 252.225-7052 (MAY 2024) expands by its own terms, potentially making material in an organization’s stock compliant on December 31, 2026, and noncompliant one day later. A post-2026 delivery under an agreement containing that clause may be barred because of covered-country mining, refining or separation, even if the material was previously placed in inventory. Congress has changed the statutory upstream restriction to focus on the contract-award date, but contractors must still address any conflicting obligations in their existing agreements. There is a solution, however, that may delay impacts and give the supply chain more time to develop alternate sources for samarium-cobalt or neodymium-iron-boron magnets, tantalum, or tungsten, whose upstream supply chains involve a covered country.
The solution derives from Revision 1 to Class Deviation 2026-O0041, which established DFARS 252.225-7961 (JUN 2026). Section 7961 ties the expanded mining, refining and separation restriction to the date of contract award rather than the date of delivery. But the deviation is not self-executing contract language: It does not silently remove section 7052 from an executed agreement. Accordingly, contractors need to be proactive.
Why January 1 Matters for Contracts Containing Section 7052
DFARS 252.225-7052 (MAY 2024) uses a delivery-date rule. Through December 31, 2026, it prohibits delivery of covered material melted or produced in a covered country and end items manufactured in a covered country that contain covered material. Beginning January 1, 2027, the clause adds mining, refining and separation to the restricted supply-chain stages. Because the clause applies that expanded rule to delivery under the contract, it can reach a 2027 delivery even when the contract was awarded and the material was placed in inventory years earlier.
The date on which a contractor bought the material does not create a safe harbor. Neither does the date of the applicable contract. If section 7052 remains in the governing instrument, a contractor must satisfy the clause as it reads on the delivery date or establish an applicable exception or authorized determination. That makes early 2027 deliveries the immediate concern and leaves little time to identify upstream sourcing, coordinate with customers and complete any necessary contract amendment.
How Section 7961 Changes the Timing Rule
Section 848 of the Fiscal Year 2026 National Defense Authorization Act revised the pending amendment to 10 U.S.C. section 4872 so that, beginning January 1, 2027, the expanded upstream restriction applies to contracts entered into on or after that date. Revision 1 implements that award-based structure through section 7961. Its mining, refining and separation restrictions apply only to delivery under a contract awarded on or after January 1, 2027. The clause separately retains the continuing prohibition on covered-country melting, production and certain end-item manufacture.
Sections 7052 and 7961 therefore differ in one critical respect: Section 7052 ties the expanded upstream restriction to the delivery date, while section 7961 ties it to the award date. That difference benefits a pre-2027 award only if section 7961 governs the instrument under which delivery occurs.

The Deviation Does Not Automatically Amend Existing Contracts
Revision 1 directs Department of Defense (DoD) contracting officers to use the deviation language for covered acquisitions, but Revision 1 does not itself rewrite an executed contract. Consistent with FAR 1.108(d), acquisition-rule changes generally apply prospectively and may be added to existing contracts by agreement. An existing prime contract, subcontract or purchase order that still incorporates section 7052 therefore should not be treated as if it already contains section 7961.
The same point applies down the supply chain. A modification to a prime contract does not automatically revise lower-tier agreements. Prime contractors must update affected flowdowns, and subcontractors should obtain written confirmation before assuming that an upstream change reaches their agreement. If sections 7052 and 7961 both appear in one instrument, section 7961 does not expressly nullify section 7052, and neither clause supplies a special order-of-precedence rule. The cleaner course is a written amendment that expressly deletes section 7052 and incorporates section 7961.
Which Contracts Need Attention Before 2027
The phrase “contract awarded” requires close attention for indefinite-delivery vehicles, task and delivery orders, options, major modifications, and lower-tier purchase orders. The FAR definition of contract includes accepted purchase orders and certain other instruments, while section 7961 does not provide a comprehensive rule for deciding when every later instrument is a new contract for this purpose. Contractors should identify the instrument under which delivery will occur, the clause incorporated into that instrument and its award date. A pre-2027 prime award may not determine the treatment of a lower-tier instrument awarded in 2027.
What Section 7961 Does Not Change
What Contractors Should Consider Doing Now
Contractors have limited time to identify affected instruments and obtain amendments before their first post-2026 deliveries. December 31 is not necessarily an absolute deadline for executing every amendment, but section 7052 begins restricting affected deliveries on January 1. Contractors should not assume that an amendment completed later will cure deliveries made while the unamended clause governed. We recommend that contractors and subcontractors consider the following steps now:
DoD issued Revision 1 in July, and less than three months remain before section 7052 expands. For companies expecting deliveries early in 2027, the practical window for reconciling contract language is narrowing. Acting now can avoid a delivery interruption involving material that section 7961 might otherwise permit under a properly amended pre-2027 award.